The Changtu CDM project has been submitted for registration to schedule, it has been listed on the EB UNFCCC website on 17th Feb 2007 for public...
The Changtu Wind Farm CDM project has obtain the approval letter from the NDRC on 14th Dec 2006; it has then passed the validation process by DN...
On December 2006, the CCH has incorporated the Zhengzhou Zhengji Xiehe energy equipment technology Co., Ltd. together with Zhengzhou Machinery R...
Recently, two subsidiaries of the company were incorporated, the Beijing Century Juhe Wind Power Operation Maintenance Company and Jilin Tianhe ...
Up to today, the 67 sets of wind power turbines were successfully installed, part of them were gone on grid and start to generate electricity. T...
Until 10th of October, the power plant has installed 43 set of wind turbines; 45 towers. Booster station is nearly competing; reverse-delivery o...
In 10th of October, the application documents of Changtu Wind power CDM project have passed the 22nd meeting of Chinese CDM council successfully...